With its glittering bright lights and surrounded by pine forests that whistle in the dark night, Dung Quat Oil Refinery in the central province of Quang Ngai looks like a small but beautiful city.
It is Vietnam’s first oil refinery and has a capacity of 6.5 million tons of crude oil a year initially. It hopes to increase this to 10 million tons in a few years.
SGGP spoke to the deputy director of the Vietnam Petrol and Oil Group (PetroVietnam), Truong Van Tuyen, about how the plant took shape.
Reeling off figures without referring to any notes, he said the factory began its trial run on July 25. Up to now, most technical processes have been tested thoroughly.
Around 52,500 tons of diesel have been processed during the test run and the refinery’s readiness has been estimated at 99 percent.
Tuyen agreed to let the media visit the plant but said “you should come in the evening and also visit Cay Sau hill, which will be used as a vantage point to view the factory.”
Cay Sau hill is not too high but with a seven-kilometer road still under construction, conditions very muddy and difficult. At the top of the hill flies the national flag.
From the top, the refinery looked a picture in the afternoon sunlight. We could see a crude oil tank that can contain 390,000 cubic meters (around 210,000 tons) and the actual refinery with its huge distilling towers where petrol products, LPG, and propylene are produced.
To build this giant refinery, there were sometimes 15,000 people and 500 foreign experts, working.
The engineers and workers who built it would surely do better when they work on future refinery projects, he said.
On November 30 it received its first batch of 80,000 tons of crude oil from Bach Ho (white tiger) oil field for a test run.
Tuyen said 25 days after Tet, the first Vietnamese-made petroleum products will come to the market.
Monday, February 2, 2009
It’s all systems go for Vietnam’s first oil refinery
Tuesday, January 13, 2009
Over 280b dong to upgrade National Road 20
Viet Nam Road Department yesterday started work on upgrading the National Road 20 linking Lam Dong highland province with HCM City and south-eastern provinces, with a total investment capital of over 280 billion dong under BOT (Building-Operating-Transferring).
The project will have three bidding packages. The road is 18 kilometres long.
The construction time is estimated to be 24 months. Investors are allowed to collect refund fee within eight months from the work being out into operation.
Government approves proposals for international seaports
Deputy Prime Minister Hoang Trung Hai has recently approved proposals from relevant authorities and investors related to speeding up the rate of building international seaports.
To speed up the building of the $200 million Van Phong International Transit Port in Khanh Hoa province, deputy Prime Minster Hoang Trung Hai approved the Ministry of Transport proposal to authorize Vietnam National Shipping Lines to make direct decisions on related issues in future.
Mr. Hai has also allowed Vietnam National Shipping Lines to calculate the total amount of investment capital needed for the project and then outline schemes to mobilize sufficient funds for it.
Regarding the choice of contractors for tendering, especially those for building the first two wharfs, Mr. Hai has requested the Ministry of Transport to call for prestigious and experienced foreign investors that have enough financial capability to join the project.
When completed, Van Phong will be one of the largest ports in Asia, which can receive container ships of up to 10,000 -12,000 tons.
Mr. Hai has also assigned the Ministry of Industry and Trade to approve the site where the 2,640 MW Van Phong Thermo power plant will be built in Khanh Hoa province.
The project will cost $3.8 billion and is scheduled to be commercially operational by the end of 2014 and be completed 2015.
For the Hai Phong International Gateway Port, Mr. Hai has approved relevant authorities’ proposal that $8 million be used for the upgrading the port’s facilities to make it ready for the task of calling for ODA (Overseas Development Assistance) for the second phase of building.
Located in Cat Hai District, in the north of Hai Phong City, the 472 hectare port is worth over $435 million. It has a total berth length of 3,200 meters for vessels with a capacity of 80,000 DWT. The port’s cargo capacity is 35m tons a year.
Vietnam completes construction of first dredger
The Ben Kien Shipbuilding Industry Company launched a 2,800 cu.m dredger on January 12, the first vessel of its kind to be built in Vietnam .
At 80m long and 15m wide, the ‘Elbe’, ordered by the Netherlands ’ Bagger Bedriif Deboer Holdings Company, is fitted with state-of-the-art machinery, enabling it to dredge silt-laden riverbeds or the seafloor to a maximum depth of 28m.
The company has previously constructed six container ships for its partners in the Netherlands.
BP to supply crude oil for Dung Quat refinery
The oil giant, British Petroleum, is to supply crude oil to Dung Quat, Vietnam ’s first oil refinery, in accordance with a contract signed in Hanoi on Jan 12 by the British company and Vietnam ’s PV Oil and BSR firms.
PV Oil is responsible for negotiating with BP over the purchase of crude oil, which will gradually replace the supply of crude from Vietnam ’s Bach Ho (White Tiger) oil field, whose output is expected to decrease in the future.
Dung Quat refinery, which is to commence operations on Feb 25, is designed to process 3.5 million tonnes of oil during 2009, or 70-75 barrels per day. Its annual capacity is set to increase to 6.5 million tonnes, equivalent to 100-145 barrels per day in subsequent years.
Once fully operational, the refinery will meet 30 percent of domestic demand. Vietnam currently imports 13 million tonnes of petro and oil per year.